Keeping Control.
Configuration management is a method for administering an evolving, and often
interrelated, set of products and project documentation. The application of
effective
procedures should ensure the accurate and up-to-date documentation and
distribution of all relevant product components and project information.
Configuration Management should be applied to projects of any significant size,
and should be the day-to-day responsibility of a single individual. The
configuration management plan should be produced as part of the project
initiation document (PID). Where products constitute sub-assemblies of more
complex products, the approach used must be able to track all such
relationships, enabling the accurate analysis of all associated information. All
of the products and documents that require the administrative controls of the
configuration management method being used are called configuration items.
Initially the overall end-product (or project deliverable) can, theoretically,
be viewed as the only identifiable configuration item. However, an increasing
number of configuration items will usually be identified as the end product is
sub-divided into the manageable elements represented in the work breakdown
structure.
A configuration item description record should be used to record the information
needed to identify and track each configuration item through its development
life cycle. Configuration control is concerned with the procedures for the issue
and submission of configuration items. These procedures should address both
physical and electronically stored configuration items. Configuration audits
consist of cross checking the configuration item description records with the
current version of the configuration item as held in its development folder. In
the first instance, a configuration item should be created and documented as the
first version. The configuration item may then undergo a number of modifications
as it is tested and errors corrected, or as changes are requested and these
subsequent submissions should be reflected by an increasing version number. The
first baseline for a configuration item will be established when the
specification of the item has been prepared, reviewed and agreed.
Subsequent baselines will normally be established at points at which the
configuration item is ready to be used as a basis for further work in which a
major transformation of it will take place. A release consists of a specified
set of products from one or more base-lined configuration items, which are
issued as a set for a specific purpose. Releases should be authorized by the
project or sub-project manager.
Configuration Management Plan.
The configuration management plan should be produced as part of the project
initiation document (PID), for approval by the project owner at project
initiation. Where
appropriate configuration management should continue throughout the life of the
delivered end-product, and therefore the approach adopted should be transferable
to the client organizations operational and maintenance sections at the end of
the project. If other projects within the organization are using a configuration
management method then this should be seriously considered for the current
project, particularly if the two projects share any areas of interest. The
following list is the recommended minimum scope required of a configuration
management method. This should be adjusted to suit the needs of each particular
project.
Synopsis & Purpose - This should provide a brief overview of the plan and
highlight any differences in approach to existing site standards - with a
justification thereof. It should also explain the aim of the activities defined
in the plan. Any dependencies on configuration management plans from other
projects should be identified.
References - This serves to identify all other standards to be used by the
configuration management method.
Configuration Item Identification - This section should specify the naming and
numbering conventions to be used for all types of configuration items.
Scope - This should outline the full range of tasks in the plan, in particular
it should consider all areas that have links with associated projects or that
may be bringing in prefabricated components. Any special operating requirements
should also be considered. It should also define which items are to be managed
under the plan and which are outside the plans control.
Definitions and Abbreviations - This is a short glossary; that should be
produced to support the plan if necessary.
Responsibilities - The clearest representation is a responsibility matrix,
showing which role should carry out each activity in the plan. The configuration
administrator will feature often.
Filing - This section defines in detail the filing structure to be used for each
category of configuration item. This should cover hardware, software,
documentation, human and machine readable items.
Document Issue Procedures - This should define the procedures to be used for
issuing and distributing copies of all managed documents.
Security - This should define the access security measures for the master copies
of all configuration items.