Understanding Cumulative Cost Curves.
The three variables BCWS, BCWP and ACWP should be plotted graphically as the
project progresses. Note that the solid curves represent actual data and the
dotted curves represent projections. It is these 'cumulative cost curves' that
enable analysis of the project to be undertaken at any point in time. Only the
BCWS curve can be plotted in advance, the other two cumulative cost curves are normally plotted on a
weekly or monthly basis.
The ACWP curve is plotted by measuring the actual work done as recorded on
timesheets.
The BCWP can be calculated by multiplying the assessed percentage complete by
the budget (BCWS).
Establishing Cost Variance.
The cost variance can be established at any point in time by referring to the
difference between ACWP and BCWP. Remember, cost variance is a measure of the
deviation between the earned value and the actual cost of the work performed.
Schedule Variance – Cost.
The schedule variance (cost) can be established at any point in time by
referring to the difference between BCWS and BCWP. Remember, schedule variance
is a measure of the deviation between the actual progress and the planned
progress. This variance is normally converted to a percentage value to avoid
representing the schedule variance in cost units.
Schedule Variance – Time.
The schedule variance (time) can be established at any point by referring to the
difference between BCWS and BCWP - but with reference to the horizontal axis.
Monitoring Efficiency.
In addition to calculating the cost and schedule variances earned value analysis
can also supply figures that quantify how efficiently the project is
progressing. The formulae on this page provide feedback on performance
efficiency in relation to the Budgeted Cost of Work Performed. An index value of
1 indicates that the project is entirely in line with the plan. An index value
>1.0 indicates exceptional project performance. An index value < 1.0 indicates
performance below planned expectations.
Budget Variance.
As a project progresses it is usually important to monitor the overall costs of
the project in relation to the original budget. Budget variance is a key measure
of the
anticipated cost of the whole project at some time after project initiation.
Once again a negative value indicates a budget overrun.
ECAC, or Estimated Cost at Completion is a revised prediction of how much the
project will cost (it takes into account the money spent so far and your current
estimate of the total resources required to complete the project). BCAC, or
Budgeted Cost at Completion is the original budget for the whole project.
Monitoring Progress.
One of the most important benefits of EVA is the calculation of the overall
percentage complete of either a complete project or sub-project. This is
obtained by dividing the total earned value, which is the sum of all the
individual earned values, by the original budget. It is this variable together
with the predicted final cost and cost variance that will be of most interest to
senior management.
All Material - Copyright Interactive Training Technologies (2000 - 2005). All Rights Reserved.