Variance Analysis.
The difference between the costs detailed in the plans and the actual costs is
called variance. In order to calculate variance, up to date and accurate
information is essential - providing a clear picture of the extent to which
tasks are complete and the expense incurred to date. Clearly variance can be
calculated for those tasks that have been completed, but for tasks that are
partially completed the calculations are more complicated. A positive variance
indicates that a project is under-spending whereas a negative variance indicates
that a project is suffering from over-spend. In the above example the 'actual
cost' has been established as 12,500 (cost) units and you can see the effect on
the variance by altering the estimated 'cost to complete'.
Applying Variance.
Variance can be used to quantify the difference between the planned costs and
the current planned costs, at whatever level is required - for example, for the
project as a whole, for a sub-project, a group of related tasks or for
individual tasks. Variance is usually expressed as a percentage, enabling the
divergence to be quantified in proportional terms. Remember a negative variance
indicates that the project is suffering from overspend.
Limitations of Variance Analysis.
This variance analysis can lead to the identification of certain types of task
that frequently overrun their budget whilst other tasks may be seen to regularly
come in under their budget. Occurrences such as these require further
investigation in order to identify potential efficiency gains. The major problem
with a variance analysis approach to project monitoring is the amount of time it
takes to establish actual costs. On the majority of large projects, supported by
a typical accounts department, there will be a time lag of around 6 weeks before
spend information can be accurately reported.
The monitoring cycle can be so long that it renders the application of control
impossible. Typically, by the time a problem has been identified through
variance analysis it is too late to take corrective action. This is a major
shortcoming of variance analysis and highlights the need for a monitoring system
that depicts the current status of the project more effectively. A more
practical approach, known as earned value analysis, is based on variance
analysis and is introduced in the next section.
All Material - Copyright Interactive Training Technologies (2000 - 2005). All Rights Reserved.