The Prevailing Culture.
The accuracy and timeliness of the data collection procedures will also be
influenced by a series of practical issues and the overall attitude of project
management staff towards reporting progress. The mechanisms that the organization already has in place to
support project related work may well influence the practical results of
applying a 'planned' reporting structure. If a variety of suitable forms and
reports are already in use then the adoption or adaptation of these may well
streamline and enhance practical data collection. Project team members will
almost certainly develop an individual, or even a collective, attitude towards
the value and importance of the data collection and progress reporting mechanisms being
applied. The more positive this is the better the implications for the quality
and timeliness of future project data.
One factor that can greatly influence the project team member’s attitude towards
the data collection exercise is the perceived objectivity of those staff
collecting and
reporting the data. If project staff develop a mistrust of the data collection
and reporting process then they may start to adjust their figures to correct for
misrepresentation. Another important factor that can influence project staff
attitude towards the data collection process is the way that it is acted upon by
management. For example if management are viewed as heavy handed or punitive in
respect of reported overruns then it will increase the likelihood that staff
will attempt to disguise such occurrences in the information they report.
Key Control Measurements.
The nature and quantity of data that is to be collected will vary - project by
project. However a variety of essential measures should be included as a
starting point when specifying the data requirements for a forthcoming project.
The plans should include an anticipated start date for the project, however the
date on which the project actually starts needs to be recorded. The plans should
include a planned finish date for the project, however the date on which the
project actually ends needs to be recorded. This measurement should reflect a
continually updated value of the proportion of planned project time remaining.
The remaining duration can be expressed in a variety of ways including as a
percentage of the overall planned duration of the project.
The percentage complete should be a continually updated figure that represents
the percentage of overall project work that has been completed. It should be
apparent that this value and the remaining duration may be monitored in
parallel. The percentage incomplete should be a continually updated figure that
represents the percentage of overall project work that has not been completed.
This value, along with the previous two, should represent a good indication of
progress against the plans. The man-hours used by a project frequently represent
one of the major expenses. Furthermore human resources are often the most
critical resources to secure for the project - therefore the monitoring of human
resource usage, often against type of resource, is a common project monitoring
device.
Projects use resources, both consumable, like money, and non-consumable, like
human resources. Every project is subject to resource limits - for example, the
overall budget, the availability of certain key staff, and so on. The use of all
resources needs to be carefully recorded. Careful monitoring of the projects
expenditure, in relation to the progress should be seen as being of the utmost
importance.
Over-Reporting Illustrated.
People tend to be optimistic when measuring how far a task for which they are
responsible has progressed. This can be either the result of natural optimism or
used as a means of disguising the true status of a particular task. This is
known as 'over-reporting' and it is essential that the project manager is aware
of this common problem and seeks to minimize it.
This diagram represents a typical over-reporting scenario.
At the start of week 1, the estimated 'percentage complete' of the activity is
zero.
At the start of week 2, the natural optimism that is a characteristic of most
people has resulted in a report of 'progress to date' being significantly ahead
of actual progress.
At the start of week 3, as the work of the project becomes more advanced a
variety of factors may lead to the continued over-reporting of progress.
Optimism may still be an issue as may the desire to maintain the rate of
progress that was reported earlier. This latter problem is likely to be
compounded if management actively encourage the reporting of rapid progress.
At the start of week 4, the team starts to realize that their progress claims
have seriously over-reached the actual work completed. However it can be very
difficult for them to admit that such an exaggeration has been made, and even
more difficult to report negative progress.
At the start of week 5, the reported progress falters significantly as the team
has no room for manoeuvre - they cannot report that the task is complete or that
negative progress has been made. Over-reporting often leads to a situation where
a project is ‘apparently’ 90% complete forever.
Maximize Your
Objectivity.
Projects which rely on subjective reporting mechanisms often suffer from the
over-reporting syndrome - where 90% of activities appear to be 90% completed 90%
of the time and yet nothing is ever delivered within the parameters of the
base-lined plan. It is a fact that projects suffer from delays and this is not
necessarily the result of bad management. However, management may compound the
over-reporting problem if they are seen to react enthusiastically to reports of
progress ahead of that planned whilst reacting negatively to any progress
shortfalls. The best way to avoid over-reporting is to implement objective
measures and minimize the degree of monitoring that is based on subjective
feedback. All project staff should be made aware that hiding delays out of fear
and embarrassment can do serious damage to the project. The sooner a problem is
highlighted the greater the time in which to take corrective action. The hiding
of problems may result in the opportunity for solving them disappearing.
All Material - Copyright Interactive Training Technologies (2000 - 2005). All Rights Reserved.