pert charts free online tutorial Navigation
    
Pert Charts - Free Online Tutorial
The information in this free Pert Charts tutorial is taken from "GetAhead in Project Management". GetAhead in project management distils a 4-day class-based course into a highly focused self-study course. Delivered direct to you, each course installs in under one minute and provides you with unlimited training for a lifetime - it's like having your very own project management training library.
        
The Project Management self-development program is available in the following formats...
   
                                                                          
                eBook                                      3 Multimedia CD-Roms              eBook & 3 Multimedia CD-Roms
    
    
 

Free Pert Charts Tutorial

    
 

Introduction
PERT charts contain detailed information relating to the activities necessary to produce the required products.

The PERT chart should be developed from the product flow diagram by examining the tasks needed to produce the products required. The resources required to complete each product should be identified and the PERT chart should then be updated to reflect these.

An alternative style of diagram to the PERT chart is the arrow diagram and both of these techniques have their advantages. The main difference is that on the arrow diagram the activity information is shown on the relational link, whereas the PERT chart shows activity information within the node, or activity box. The use of either technique should produce the same result.

PERT charts have become established as the most popular planning technique and have been included in project management software packages.

Symbols Used
PERT charts are made up of a series of activity boxes, each of which depicts a discrete activity or task. Each activity box may contain up to 7 items of information.

The top line of the box reflects the earliest point at which the activity could start and finish. The center line should contain descriptive information about the activity and the bottom line should be used to reflect the latest start and finish times.

 

Gantt Chart - example PERT chart
PERT Chart

    
  In this example, activity A must be completed before activity C can begin as indicated by the line that joins the two activity boxes.

Activity A requires 5 days and Activity C requires 4 days. This part of the project will therefore last 9 days.

The earliest start time for activities right at the beginning of the network are set to zero. The earliest finish time for whichever input activity is the latest is used to establish the earliest start time for the dependent activity. In this example activity A is scheduled to be completed on day 5. Only then can activity C begin.

A Simple Example
In many cases an activity will be dependent on the completion of more than one preceding activity. In the example shown the two activities A and B must both be completed before activity C can begin. A requires 5 days, B requires 4 days and C requires 4 days.
 

  Activities A and B can be carried out in parallel as they are not dependent upon each other. In this example this part of the project will also last 9 days.

Determining the relationships between activities can be a complicated process and may require a substantial amount of discussion involving numerous personnel across the various departments that may be concerned.

The process of identifying relationships between the activities should only be concerned with logical requirements, in other words it should be assumed that there are no resource constraints when drawing the PERT chart. This issue has then to be addressed and appropriate adjustments made. Resolving resource shortfalls and conflicts is the scope of resource planning and scheduling.

Diagrammers may find it useful to produce sub-diagrams and use these to conduct a brainstorming approach to identifying all possible relationships, prior to building the final network. The project will need to be monitored at various points to ensure that its business and technical integrity is being maintained - the PERT chart should also reflect these activities.

PERT charts, contain detailed information relating to the activities necessary to produce the required products. It should be developed with reference to the product flow diagram.
 

    
  The top line of the activity box reflects the earliest time at which the activity could start and finish. The centre line should contain descriptive information about the activity and the bottom line should be used to reflect the latest start and finish times. The lines that join activity boxes are used to represent dependency between the activities.
    
  Identifying Spare Time
Reading through the PERT chart from left to right gives the total duration of the plan. Reading back through the network, subtracting each duration, shows those activities that have any spare time. This spare time, known as float, is a very useful concept in relation to resource scheduling and smoothing.
 

    

  In the example shown activity R is dependent upon the completion of both of the activities P and Q. However activity P is scheduled to take 5 days whilst Q should be completed in 2 days.

The area of work represented by this part of the network should last 12 days. Activity Q has a float of 3 days - so activity Q could start up to 3 days late or take an extra 3 days to complete without delaying the start of the subsequent activity (R).

Reading back through the PERT chart, subtracting each duration, shows those activities that have any spare time. This spare time, known as float, identifies parcels of time that can be used to introduce flexibility into the production sequence.

All planning should be iterative, and the drawing of the PERT chart may highlight further products which need to be added to the work breakdown structure and the product flow diagram.

The Critical Path

Once the resources required to complete each product have been identified and the PERT chart updated to reflect these, then the start and finish dates can be added. With the shape and size of the project now visible, the total cost of the resources for each planning period can be calculated.
 

  The PERT chart also clearly identifies the critical path (shown in red above), which is the sequence of related activities which will take the longest time. The critical path is an invaluable concept in project planning - as it defines that sequence of activities that should take the longest time.
      
  Total & Free Float
The above network represents a small project. The activities that are on the critical path (shown in red) have no float, whilst those that lie off the critical path can have an associated float.
   
 

    
  In addition to the float associated with a specific activity, two other types of float need to be considered.
       
 

   
  Total Float (shown in yellow above) is shared with all of the other activities in the arm. Therefore using the float in one activity will reduce the float available for the other activities. For example, in the arm PQ the total float is 19. This is because the dependent activity L has a latest start of 23 and the total duration of the PQ arm is 4. That is 23 minus 4 equals 19.
     
 

   
  Free Float (shown in yellow above) is the amount of float that the activity can use up without affecting the earliest start of any other activity. Only activities that precede a junction can have free float. For example, the earliest finish of activity Q is 4. The earliest start of the dependent activity L is 12. Therefore the completion of activity Q could be delayed for a maximum of 8 without affecting the earliest start of activity L.

Float is a measure of the amount of time an activity can be delayed without affecting subsequent activities. The amount of float indicates the extent of time that the activity can be delayed without putting back the end date of the overall project. Activities that have an associated float are natural candidates to be delayed when other activities are suffering from problems or overruns.
     
 

   
  The critical path (shown in red) is defined as the series of activities which have zero float. There will always be a critical path running through a project from the first activity to the last. However any task, if subjected to sufficient delay, may itself become critical - and this will occur at the point when its float has been entirely consumed by the passage of time.

In larger projects, particularly as the project nears completion a number of the arms of the network may contain zero float i.e. the project may contain numerous critical paths. The critical path is an important feature in project planning and control and is usually highlighted on the network in some manner - e.g. bold print, red or a different style of line. It is important to remember that the critical path is not defined at the initial planning stage and then set in stone.

As the project progresses and planned activities overrun the network should be frequently updated to ensure that it continues to reflect the true status of the project. The failure to do this is a common reason for projects going out of control and ultimately failing.

Back to Pert Charts
     
Pert Charts - Free Online Tutorial
The information in this free Pertt Charts tutorial is taken from "GetAhead in Project Management". GetAhead in project management distils a 4-day class-based course into a highly focused self-study course. Delivered direct to you, each course installs in under one minute and provides you with unlimited training for a lifetime - it's like having your very own project management training library.
   
The Project Management self-development program is available in the following formats...
   
                                                                          
                eBook                                      3 Multimedia CD-Roms              eBook & 3 Multimedia CD-Roms
    

 

GetAhead - Free Training Resources
These free online tutorials are text only extracts taken from the GetAhead range of training courses.

Personal Skills Management Skills Technical Skills
Job Search
Interview Questions
Career Search
Career Change
Career Education
Career Planning
Salary Negotiation

Time Management Skills
Negotiating Skills
Communication Skills
Public Speaking

Nonverbal Communication
Meeting Planning

Project Management Training
Configuration Management
Gantt Chart
Pert Charts
Data Flow Diagrams
Data Modeling
Entity Relationship Diagram

 

 

 

 

Personal Development        Soft Skills              Management Skills          Management Training         Leadership Skills
Distance Learning               Open Learning       Team Building                Professional Development   Training & Development                    
Computer Based Training    Online Training      Correspondence Course   Business eBooks                 Management eBooks        
Get Ahead                         GetAhead              Links                             Map